2018 - 2019 cycle schedule

11 June 2018 Call for Proposals
15 October 2018 Deadline for Experiment Proposals
13 November 2018 Information of the students about the pre-selection results / Invitation to the selection workshop
27–29 November 2018 SNSA/ESA Selection Workshop at ESA/ESTEC, Noordwijk (NL)
10 December 2018 Information of the students about the selection results / Invitation to the Student Training Week (STW)
1115 February 2019 Student Training Week (STW) and Preliminary Design Review (PDR) at DLR Oberpfaffenhofen (DE)
15 May–17 May 2019 Critical Design Review (CDR) for BEXUS 26/27 experiments at ESA/ESTEC, Noordwijk (NL)
13–17 June 2019 Critical Design Review (CDR) for REXUS 25/26 experiments at DLR Oberpfaffenhofen (DE)
July/August 2019 BEXUS 28/29 Integration Progress Reviews (IPRs) at the student team institution
August/September 2019 REXUS 27/28 Integration Progress Reviews (IPRs) at the student team institution
August/September 2019 BEXUS 28/29 Experiment Acceptance Review (EARs) at the student team institution
1828 October 2019  BEXUS 28/29 Launch Campaign at SSC Esrange/Kiruna (SE)
November 2019 REXUS 27/28 Experiment Acceptance Review (EARs) at the student team institution
913 December 2019 Scientific Payload Integration Week for REXUS 25/26 at ZARM-FAB, Bremen (DE)
January 2020 REXUS 27/28 Bench Test, DLR Oberpfaffenhofen (DE)
March 2020 REXUS 27/28 Launch Campaign at SSC Esrange/Kiruna (SE)

2019 - 2020 cycle schedule

17 June 2019 Call for Proposals
14 October 2019 Deadline for Experiment Proposals
November 2019 Information of the students about the pre-selection results / Invitation to the selection workshop
26–28 November 2019 SNSA/ESA Selection Workshop at ESA/ESTEC, Noordwijk (NL)
December 2019 Information of the students about the selection results / Invitation to the Student Training Week (STW)
February 2020 Student Training Week (STW) and Preliminary Design Review (PDR) at SSC Esrange (SE)
May/June 2020 Critical Design Review (CDR) for BEXUS 30/31 experiments at ESA/ESTEC, Noordwijk (NL)
18–22June 2020 Critical Design Review (CDR) for REXUS 29/30 experiments at DLR Oberpfaffenhofen (DE)
July/August 2020 BEXUS 30/31 Integration Progress Reviews (IPRs) at the student team institution
August/September 2020 REXUS 29/230 Integration Progress Reviews (IPRs) at the student team institution
August/September 2020 BEXUS 30/31 Experiment Acceptance Review (EARs) at the student team institution
October 2020 (10 days) BEXUS 30/31 Launch Campaign at SSC Esrange/Kiruna (SE)
November 2020 REXUS 29/30 Experiment Acceptance Review (EARs) at the student team institution
December 2020 Scientific Payload Integration Week for REXUS 29/30 at ZARM-FAB, Bremen (DE)
January 2021 REXUS 29/30 Bench Test, DLR Oberpfaffenhofen (DE)
March 2021 REXUS 29/30 Launch Campaign at SSC Esrange/Kiruna (SE)