Entry 5: Proba-2 powered up

285 views 0 likes
ESA / Enabling & Support / Space Engineering & Technology / Proba Missions

6 September 2009 – The 45-minute bus ride to the MIK is a last chance to grab some rest before the work day begins in earnest.

In the clean room activities proceed with a successful inspection of the spacecraft's solar arrays, checking the health of its battery and preparing for propellant filling. In the meantime in the EGSE chamber preparations take place for powering up and full functional testing of the spacecraft.

At 11:30 comes an exciting moment: the first power up of Proba-2 after the long trip from its homeland. After nominal boot-up of the onboard computer, the rest of the day is spent verifying the full functionality of each and every electronic unit of the platform. The team is pleased to find that their 'baby' Proba-2 is now not only safe in Russia but also alive and kicking.

Related Links

Proba-2, final checks
Enabling & Support

Entry 1: Belgium says goodbye to Proba-2

282 views 0 likes
Read
Loading of Proba-2 container in cargo plane at Brussels airport
Enabling & Support

Entry 2: Proba-2's journey to Plesetsk

271 views 0 likes
Read
Transport of Proba-2 container to the MIK
Enabling & Support

Entry 3: Unpacking after the trip

210 views 0 likes
Read
Opening of the Proba-2 satellite container in the cleanroom
Enabling & Support

Entry 4: Proba-2 unloaded and ready for inspection

230 views 0 likes
Read
Hoisting of satellite from its container and assembly of integration dolly
Enabling & Support

Entry 5: Proba-2 powered up

285 views 0 likes
Read
Inspection of Proba-2 internal compartments
Enabling & Support

Entry 6: End-to-end testing

301 views 0 likes
Read
Filling of the propulsion tank with xeon
Enabling & Support

Entry 7: Filling Proba-2 up with xenon

293 views 0 likes
Read
Mounting of the first deployable solar panel
Enabling & Support

Entry 8: Proba-2 gains a solar panel

356 views 0 likes
Read
Mounting of solar panel
Enabling & Support

Entry 9: Proba-2 gains its second ‘wing’

237 views 0 likes
Read
Proba-2 with solar panels mounted
Enabling & Support

Entry 10: Completing Proba-2

232 views 0 likes
Read
Proba-2 final full functional test
Enabling & Support

Entry 11: Putting Proba-2 to the test

258 views 0 likes
Read
Proba-2 launch team group picture at the museum
Enabling & Support

Entry 12: Checking launch tower links

245 views 0 likes
Read
Proba-2 back in its storage container in the cleanroom
Enabling & Support

Entry 13: Letting SMOS take its turn

221 views 0 likes
Read
Proba-2 team arrival at Plesetsk Cosmodrome
Enabling & Support

Entry 14: Second phase of Proba-2 launch campaign begins

258 views 0 likes
Read
ESP mounting on the final panel
Enabling & Support

Entry 15: Last bolts tightened on Proba-2

254 views 0 likes
Read
Proba-2
Enabling & Support

Entry 16: A short journey off the ground – Proba-2 mated to…

246 views 0 likes
Read
Proba-2 in its final launch position, on top of Breeze
Enabling & Support

Entry 17: Proba-2 mated onto Breeze upper stage

299 views 0 likes
Read
Removal of Proba-2 protective covers
Enabling & Support

Entry 18: Encapsulated, Proba-2 vanishes from view forever

236 views 0 likes
Read
Encapsulation
Enabling & Support

Entry 19: Proba-2 in place and powered up

240 views 0 likes
Read
SMOS, Proba-2 and Khrunichev teams
Enabling & Support

Entry 20: Rail ride to the launch pad

264 views 0 likes
Read
Joined dress rehearsal of Proba-2 and SMOS in MCC
Enabling & Support

Entry 21: Far-flung dress rehearsal for launch

490 views 0 likes
Read