ESA title
Play
$video.data_map.short_description.content
Enabling & Support

Ariane 6 development on track

06/06/2019 6416 views 67 likes
ESA / Enabling & Support / Space Transportation / Ariane

Europe’s Ariane 6 launch vehicle is set to debut with a commercial mission in 2020 – industry is carrying out the final tests and starting production. The Ariane 6 launch zone at Europe’s Spaceport in French Guiana is near completion.

Ariane 6’s core stage is powered by the Vulcain 2.1 engine, its upper stage is powered by the reignitable Vinci engine. Strapped on to the core stage will be two or four P120C solid-fuel boosters, a technology shared with Vega-C, to provide thrust at liftoff.

Latest developments

Play
$video.data_map.short_description.content
Vulcain 2.1 preparation and first test
Access the video

Since a previous update on progress in December, Ariane 6 has moved to the final stage of development where tests qualify the designs that will guide production. 

At DLR-Institute of Space Propulsion in Lampoldshausen, Germany, hot-firing tests of the Vulcain 2.1 engine are close to completion. Vinci engine hot firing tests have finished successfully. A team of experts will examine the results of these tests and once these reviews are successful, these two engines will be qualified for flight.

P5.2 test stand
P5.2 test stand

A new test facility, the P5.2, at the same DLR site was inaugurated in February and will enable testing of the complete Ariane 6 upper stage. This upper stage will come from ArianeGroup in Bremen, Germany who are currently focusing on engine integration, final operations and testing. MT Aerospace, also in Bremen, are supplying the fuel tanks.

Ariane 6 tank for the core stage
Ariane 6 tank for the core stage

An ArianeGroup facility in Les Mureaux, France, hosts the largest friction stir welding machines in Europe for producing the Ariane 6 cryogenic tanks for Ariane 6’s core stage. The Aft bay, which secures the Vulcain 2.1 engine to the core stage is in production and being integrated at the same location.

Hot firing of P120C solid rocket motor for Vega-C
Hot firing of P120C solid rocket motor for Vega-C

The first qualification model of the P120C strap-on booster configured for Vega-C was static fired in January on the test bench at Europe’s Spaceport (watch the video here).

The second qualification model, configured for Ariane 6, will be tested at the beginning of next year. The 11.5 m long and 3.4 m diameter insulated P120C motor case is made of carbon composite built in one piece by Avio in Colleferro, Italy.

P120C gains a nozzle
P120C gains a nozzle

At ArianeGroup in Issac and Le-Haillan, France, new fully robotic production lines have the capability of increasing production by 30% to assemble the rear skirts and build nozzles for the P120C strap-on solid rocket motors. MT Aerospace in Augsburg, Germany, are supplying the rear skirts.

First half-shell of Ariane 6 fairing
First half-shell of Ariane 6 fairing

RUAG Space in Switzerland has recently produced the first large half-shell of the fairing for Ariane 6. Built in one piece using carbon fibre, it was cured in an industrial oven instead of an autoclave – a process developed with the help of ESA.

Preparing for flight

Early next year, the P120C solid rocket motor configured for Ariane 6 will be test fired in Kourou to qualify it for flight. Ariane 6's upper stage will be test fired at the DLR-Institute of Space Propulsion in Lampoldshausen, Germany. A test model Ariane 6 will also start combined tests in Kourou, including a static fire of the core stage engine, the Vulcain 2.1.

Play
$video.data_map.short_description.content
Time for answers: Ariane 6
Access the video

Ariane 6 launch base near completion

The Ariane 6 launch base at Europe’s Spaceport is on track and near completion. The main structures include the Launch Vehicle Assembly Building, the mobile gantry, and launch pad.

The launch vehicle assembly building used for horizontal integration and preparation of Ariane 6 stages before rollout to the launch pad, is complete and tools are now being installed.

The 90-metre tall metal frame of the mobile gantry is fully constructed and in February cladding started. The mobile gantry houses Ariane 6 until it is retracted before launch. The first rolling test of this 8200-tonne structure will be performed this summer.

The launch pad flame deflectors were installed at the end of April. They will funnel the fiery plumes of Ariane 6 at liftoff into the exhaust tunnels buried deep under the launch table. The nearby water tower has also been installed.

The first four levels of the mast have been mounted and welded and in February the integration started of the fluidic lines that will interface with the launch vehicle.

The LH2 and the LOX plants that produce and store the liquid hydrogen and liquid oxygen needed to fuel the launcher’s engines are complete.

 

 

 

Rockets are the backbone of all space-based endeavours. ESA in partnership with industry is developing next-generation space transportation vehicles, Ariane 6, Vega-C, and Space Rider. At Space19+, ESA will propose further enhancements to these programmes and introduce new ideas to help Europe work together to build a robust space transportation economy. This week, take a look at what ESA is doing to ensure continued autonomous access to space for Europe and join the conversation online by following the hashtag #RocketWeek

Related Links