• → European Space Agency

      • Space for Europe
      • Space News
      • Space in Images
      • Space in Videos
    • About Us

      • Welcome to ESA
      • DG's News and Views
      • For Member State Delegations
      • Business with ESA
      • ESA Exhibitions
      • ESA Publications
      • Careers at ESA
    • Our Activities

      • Space News
      • Observing the Earth
      • Human Spaceflight
      • Launchers
      • Navigation
      • Space Science
      • Space Engineering
      • Operations
      • Technology
      • Telecommunications & Integrated Applications
    • For Public

    • For Media

      • Media
      • ESA TV
      • Videos for professionals
      • Photos
    • For Educators

    • For Kids

    • ESA

    • Meteosat Second Generation

    • Observing the Earth

    • About MSG
    • MSG overview
    • Why we need MSG
    • How MSG works
    • Spacecraft details

      • Stabilisation
      • Architecture
      • Communications
      • SEVIRI
      • GERB
      • Search & Rescue
    • Building and flying MSG
    • Designed for space
    • Reaching orbit
    • Launch and early orbit phase
    • The future
    • Next steps
    • Beyond MSG and MetOp
    • Multimedia
    • Image Gallery
    • Video Gallery
    • Wallpapers
    • Screensavers

    ESA > Our Activities > Observing the Earth > Meteosat Second Generation

    Part 5: 13 - 19 November

    Toroidal Pattern Antenna

    Sunday 13 November
    No work during the Sunday, but this did not mean staying in bed! ESA had invited the combined MSG-2 team to join for 'go-karting' in Macouria. The track was reserved from 09:00 until 12:00 and a competition was organised. This was followed by a buffet. There was also a possibility to go 'Quad biking'. Despite the fact that the track was bone dry (those in the know tell you its a lot more fun when the jungle is wet), it was good fun. A few adventurous souls went flying in Ultra lights, some of them with very mixed feelings, vowing to never do this again (You said this already in 1991 Leonie)!

    All in all, it was a great day for team-building, and we have to say that the MSG-2 team-spirit is very good.

    Monday 14 November
    The flight batteries have been installed and torqued definitively (we hope !) on the spacecraft; the spare battery destorage has started. For the UPS (Unified Propulsion System), the regulator and thrusters line final pressurisation have been performed. Flight/Non-flight equipment inspection has started. The SEVIRI baffle cover (which will be ejected during flight) finalisation has been performed.

    Tuesday 15 November
    The flight batteries have been connected, with all functions related to charge, discharge and monitoring being tested. The TPA (Toroidal Pattern Antenna) and UHF (Ultra High Frequency) flight coax cable have been installed.

    In parallel the inspection of Building S5-A for the spacecraft filling operation has been done. This building is specifically designed for safety precautions needed for the hazardous operation with toxic liquids. MSG-2 will move to this building at the end of the health tests.

    MSG-2
    SAP installation

    Wednesday 16 November
    The flight/non-flight inspection has started; this inspection is being performed without the Solar Arrays Panels installed - the spacecraft being open and fully accessible - allowing checking to see if all equipment is in its flight configuration.

    The preparation for the filling operation has started with the set-up and validation of the fuelling equipment in the S5-A building.

    In the evening the team watched a perfect launch of V167 from various locations. The way is now clear for us!

    Thursday 17 November
    The installation of the eight Solar Arrays Panels (SAP) started. In parallel the EDA (Electronically Despun Antenna) inspection has been performed and the MLI (Multi Layer Insulation) thermal protection was finalised.


    MSG-2
    Antennas connection test

    Friday 18 November
    Solar Arrays Panels flood test started. In this test the panels are illuminated and the resulting current checked, to ensure that all electrical connections are correct and functioning properly.

    Saturday 19 November
    The preparation for the antennas connection test has started. This test checks the Radio Frequency (RF) connection between the spacecraft transmitters and receivers and the related antennas is correctly performed. Due to the relatively high RF power that is radiated, special absorber panels have to be placed around the satellite. After everything was checked by the safety department, the test started and will continue next week.

    Last update: 22 November 2005

    Rate this

    Views

    Share

    • Currently 0 out of 5 Stars.
    • 1
    • 2
    • 3
    • 4
    • 5
    Rating: 0/5 (0 votes cast)

    Thank you for rating!

    You have already rated this page, you can only rate it once!

    Your rating has been changed, thanks for rating!

    3
    Tweet
    • MSG-2 launch diary
    • Introduction
    • Part 1: 18 - 23 June
    • Part 2: 27 June - 1 July
    • Part 3: 31 October - 6 November
    • Part 4: 6 - 12 November
    • Part 5: 13 - 19 November
    • Part 6: 21 - 26 November
    • Part 7: 28 November - 2 December
    • Part 8: 5 - 9 December
    • Part 9: 12 - 20 December

    Connect with us

    • RSS
    • Youtube
    • Twitter
    • Flickr
    • G+
    • Facebook
    • Livestream
    • Subscribe
    • App Store
    • LATEST ARTICLES
    • · Earth Explorers take centre stage …
    • · The fast winds of Venus are gettin…
    • · ExoMars 2016 set to complete const…
    • · Herschel ends operations as orbiti…
    • · Europe’s largest spaceship reache…
    • FAQ

    • Jobs at ESA

    • Site Map

    • Contacts

    • Terms and conditions