ESA title
Inspection of Proba-2 internal compartments
Enabling & Support

Entry 6: End-to-end testing

606 views 0 likes
ESA / Enabling & Support / Space Engineering & Technology / Proba Missions

Monday 7 September - After the successful power up of the spacecraft the previous day, the team are busily testing of each and every element of the Proba-2 system.

These verification activities also include dedicated final end-to-end system verification using the complete radio frequency chain. In the meanwhile, in the clean room, preparation for the filling of Proba-2 experimental propulsion system is taking place. A thorough inspection of the spacecraft’s inner compartments is also performed before the final closure with its outer panels.

Proba-2 team in front of the ‘Mirny’ monument
Proba-2 team in front of the ‘Mirny’ monument

The working atmosphere with the Russians has now become excellent, and very relaxed. Europeans and Russians have become well acquainted with each other’s habits and they feel real sympathy for little Proba-2 and its 'little' launch team…

During the team's drive back to the hotel, each and every monument along the road seems to bring the heroic past of Plesetsk Cosmodrome back to life, inspiring a stop for a group photo.

Related Links

Proba-2, final checks
Enabling & Support

Entry 1: Belgium says goodbye to Proba-2

466 views 0 likes
Read
Loading of Proba-2 container in cargo plane at Brussels airport
Enabling & Support

Entry 2: Proba-2's journey to Plesetsk

482 views 0 likes
Read
Transport of Proba-2 container to the MIK
Enabling & Support

Entry 3: Unpacking after the trip

351 views 1 likes
Read
Opening of the Proba-2 satellite container in the cleanroom
Enabling & Support

Entry 4: Proba-2 unloaded and ready for inspection

417 views 0 likes
Read
Hoisting of satellite from its container and assembly of integration dolly
Enabling & Support

Entry 5: Proba-2 powered up

440 views 0 likes
Read
Inspection of Proba-2 internal compartments
Enabling & Support

Entry 6: End-to-end testing

606 views 0 likes
Read
Filling of the propulsion tank with xeon
Enabling & Support

Entry 7: Filling Proba-2 up with xenon

518 views 0 likes
Read
Mounting of the first deployable solar panel
Enabling & Support

Entry 8: Proba-2 gains a solar panel

541 views 0 likes
Read
Mounting of solar panel
Enabling & Support

Entry 9: Proba-2 gains its second ‘wing’

362 views 0 likes
Read
Proba-2 with solar panels mounted
Enabling & Support

Entry 10: Completing Proba-2

372 views 0 likes
Read
Proba-2 final full functional test
Enabling & Support

Entry 11: Putting Proba-2 to the test

451 views 0 likes
Read
Proba-2 launch team group picture at the museum
Enabling & Support

Entry 12: Checking launch tower links

369 views 0 likes
Read
Proba-2 back in its storage container in the cleanroom
Enabling & Support

Entry 13: Letting SMOS take its turn

416 views 0 likes
Read
Proba-2 team arrival at Plesetsk Cosmodrome
Enabling & Support

Entry 14: Second phase of Proba-2 launch campaign begins

398 views 0 likes
Read
ESP mounting on the final panel
Enabling & Support

Entry 15: Last bolts tightened on Proba-2

390 views 0 likes
Read
Proba-2
Enabling & Support

Entry 16: A short journey off the ground – Proba-2 mated to…

399 views 0 likes
Read
Proba-2 in its final launch position, on top of Breeze
Enabling & Support

Entry 17: Proba-2 mated onto Breeze upper stage

527 views 0 likes
Read
Removal of Proba-2 protective covers
Enabling & Support

Entry 18: Encapsulated, Proba-2 vanishes from view forever

430 views 0 likes
Read
Encapsulation
Enabling & Support

Entry 19: Proba-2 in place and powered up

376 views 0 likes
Read
SMOS, Proba-2 and Khrunichev teams
Enabling & Support

Entry 20: Rail ride to the launch pad

513 views 1 likes
Read
Joined dress rehearsal of Proba-2 and SMOS in MCC
Enabling & Support

Entry 21: Far-flung dress rehearsal for launch

889 views 0 likes
Read