Celsius Mission About the missionWhy Celsius?Daily activities Mission factsFactsheets (pdf)Official Flight KitMeet the crew Christer FuglesangMark PolanskyWilliam OefeleinRobert CurbeamJoan HigginbothamNicholas PatrickThomas ReiterSunita WilliamsCelsius Mission live ESA TelevisionNASA TV liveMultimedia Multimedia galleryVideo TalkMagic bookExhibition panelsServices
|  |  |  |  | | | Daily activities
Mission Summary
Christer Fuglesang will also be undertaking an experiment programme for the European Space Agency as
part of the Celsius Mission though this is not currently fixed to a specific day in the mission timeline.
Flight Day 1 - Launch
- Launch from Kennedy Space Center
- Shuttle to On-orbit configuration
- Activation of Spacehab
- Activation of Shuttle robotic arm
Flight Day 2
- Test the Space Shuttle’s robotic arm
- Checking the Space Shuttle heat shields
using robotic arm
- EVA preparation including testing EVA suits
- Preparations for docking with the ISS
Flight Day 3 - Docking
- Rendezvous and dock with the ISS including
Shuttle backflip manoeuvre to check heat
shields
- Hatches opened
- P5 truss moved out of Shuttle cargo bay to
overnight parked position using Shuttle and
ISS robotic arms
- Transfer equipment from Shuttle to airlock
- Checks on EVA suits. EVA tools prepared
- Fuglesang and Curbeam sealed in airlock for
the night to help flush nitrogen out of the
blood pre-EVA
Flight Day 4 – EVA 1 (Fuglesang/Curbeam)
- EVA prep
- P5 truss moved to installation location with
Station robotic arm
- Solar arrays fixed in position
- EVA: Attach P5 truss to P4 truss, relocate
grapple fixture on P5, and remove and
replace camera on S1 truss
Flight Day 5
- Transfer cargo between Shuttle and ISS
- Switch over power responsibilities from 4B
solar array on P6 truss to 4A solar array on
P4 truss
- Retract 4B solar array
- Activate Solar Alpha Rotary Joint for rotating
solar arrays on P4 truss section
- Fill and activate port-side cooling loop
- Fuglesang and Curbeam sealed in airlock for
the night to help flush nitrogen out of the
blood pre-EVA
Flight Day 6 - EVA 2 (Fuglesang/Curbeam)
- Switch ISS systems to power channels 1 and 4
- Shut down power channels 2 and 3
- EVA: Reconfigure power on power channels
2 and 3 around S0 and Z1 truss sections.
Activate port-side thermal control system,
Activate power channels 2 and 3. Relocate
Crew and Equipment Translation Aid (CETA)
carts from starboard to port-side of Mobile
Transporter.
Flight Day 7
- Transfer cargo between Shuttle and ISS
- Fill and activate starboard cooling loop
- Curbeam and Williams sealed in airlock for
the night to help flush nitrogen out of the
blood pre-EVA
Flight Day 8 EVA 3 (Curbeam/Williams)
- Switch ISS systems to power channels 2 and 3
- Shut down power channels 1 and 4
- EVA: Reconfigure power on power channels 1
and 4 around S0 and Z1 truss sections.
Activate starboard thermal control system,
Activate power channels 1 and 4. Stow debris
protection panels on mating adapter outside of
ISS Node 1. Install grapple bar on thermal box
Flight Day 9
- Configure port and starboard thermal control
power supply
- Transfer of equipment and supplies
- EVA preparations, including reconfiguring EVA suit to fit Fuglesang
- Fuglesang and Curbeam sealed in airlock for
the night to help flush nitrogen out of the
blood pre-EVA
Flight Day 10 - EVA 4 (Fuglesang/Curbeam)
- EVA: Aid retraction P6 solar array
Flight Day 11 - Undocking
- Clean-up after EVA
- Final transfer of equipment and supplies
- Hatch Closure
- Undock
- Station flyover
- Thruster burn
Flight Day 11
- Late inspection of Shuttle heat shields
Flight Day 12
- Landing preparations
- Shuttle to landing configuration
Flight Day 13 - Landing
- Landing preparations
- Deorbit burn
- Reentry
- Landing at Kennedy Space Center