Before then, a series of demanding activities must take place in the right order and on schedule. Between 9 July and 3 August, ESOC engineers will work closely with the Rosetta Science Operations Centre (SOC), at ESA's European Space Astronomy Centre, near Madrid, Spain, to check-out and verify the spacecraft's 11 instruments.
The Flight Control Team will conduct simulations on 7, 14 and 21 August to confirm and practise procedures and reactions to any unforeseen problems that may occur.
"We will practise placing Rosetta's cameras into their proper tracking mode and, as we get closer to Steins, we will actually start tracking the asteroid, and use the data to refine our estimates of Steins' orbit and how to adjust Rosetta's trajectory," said Sylvain Lodiot, an engineer assigned to Rosetta.
A series of Trajectory Correction Manoeuvres (TCM) - in which the probe's thrusters can be fired to align its trajectory relative to Steins - are possible on 14 and 28 August as well as 2, 4, and 5 September. The last TCM slots come just 36 and 12 hours before closest approach; the tight telecommand uplink windows for these must be tested and practiced.