ESA title
Astro Pi
Agency

2019/2020 European Astro Pi Challenge Timeline

5732 views 14 likes
ESA / Education / AstroPI

Mission Zero Timeline

 

Activity Date
Challenge launched 12 September 2019
Challenge ends 20 March 2020
Confirmation of flight status May 2020
Certificates delivered to teams June 2020

Mission Space Lab Timeline:

Phase Activity Date
1 Challenge launched. Phase 1: Design begins 12 September 2019
1 Deadline for Phase 1: Design 25 October 2019
2 Evaluation of Phase 1 submissions Beginning November 2019
2 Successful teams receive Astro Pi kits to use in Phase 2 Mid-November 2019
2 Phase 2: Create begins Mid-November 2019
2 Deadline for Phase 2: Create 14 February 2020
3 Announcement of teams that have successfully passed to Phase 3: Deploy 2 April 2020
3 Phase 3: Deploy April/May 2020
3 Phase 4: Analyse begins as teams receive the data collected from their experiments 6 May 2020
4 Deadline for Phase 4: Analyse 27 May 2020
4 Winners of Mission Space Lab Announced Mid-June 2020