Timeline: Mars Express support to Phoenix landing

22/05/2008 1484 views 0 likes
ESA / Science & Exploration / Space Science / Mars Express

Beginning late on 25 May, Mars Express will execute a series of pre-programmed commands specially designed to support NASA's Phoenix lander. The ESA spacecraft will conduct a high-speed slew, enabling it to track Phoenix as it enters the martian atmosphere.

Mars Express will point its Lander Communications Antenna toward Phoenix's planned entry trajectory and record signals transmitted from the lander as it plunges toward the surface during the critical entry, descent and landing (EDL) phase.

Support for Phoenix starts at 21:00 CEST when the spacecraft's MELACOM (Mars Express Lander Communications) system is switched on. Recording of radio signals transmitted by Phoenix will begin at 01:21 CEST, 26 May and end at 01:47 CEST, 26 May.

During the recording, Mars Express will conduct a high-speed slew as MELACOM tracks Phoenix, keeping Phoenix in the line of sight of the MELACOM antenna.

Upon completion of recording, Mars Express will perform a (normal) slew to Earth pointing attitude, and at 02:25 CEST on 26 May, the spacecraft will begin transmitting the recorded data, via a NASA deep-space ground station, to ESA's Space Operations Centre (ESOC), Darmstadt, Germany. The one-way signal travel time will be 15 minutes and 20 seconds. The download will be complete by 02:57 CEST, and ESOC will make the data available to NASA immediately upon receipt.

Mars Express will subsequently download the recorded data two more times to ensure redundancy. The ESA spacecraft will additionally monitor signals from Phoenix during an overflight of the landing zone, 08:12-08:23 CEST, and 14 more times during the following week. During the night of 25/26 May, Mars Express will be controlled by the Flight Control Team working in the Dedicated Control Room at ESOC.

Observations before and during Phoenix descent

It is planned that two Mars Express instruments, the High Resolution Stereo Camera (HRSC) and the Ultraviolet and Infrared Atmospheric Spectrometer (SPICAM), will be turned on for observations during the Phoenix EDL.

The observations are aimed at visually capturing the trail of the lander's trajectory to the Martian surface, studying the characteristics of the atmosphere during the lander's descent, and monitoring the lander's performance during EDL.

It is not possible to know the exact route Phoenix will take when descending to the surface, and so it is possible that the instruments may not be looking in the correct direction during the event. This makes the likelihood of success less than certain.

Nonetheless, and despite the technical and physical challenges, the Mars Express science teams are doing their best to boost the potential scientific value of the observations. In any event, highest priority will be given to tracking the lander using MELACOM.

These challenging scientific observations have never been performed at Mars before, and if successful, the knowledge gained will be useful for future missions.

In addition to the observations planned during EDL, the Planetary Fourier Spectrometer (PFS) on board Mars Express has been collecting relevant data since 8 May this year. This includes information on the physical conditions of the Martian atmosphere (temperature, pressure and density) above the expected the landing site. This data is being provided to NASA in support of their observations of the physical conditions in the atmosphere prior to landing.

Timeline

Notes:

  • S/C = spacecraft
  • CEST = UTC + 2 hours
  • Earth time = spacecraft event time + 15:20 min:sec
  • MEX: Mars Express | PHX: Phoenix | O/F: Overflight | DSS: Deep space station
  • All times subject to change. For latest times relevant to Phoenix, see NASA Phoenix website.

 

Event S/C UTC Earth UTC Earth CEST Notes
MEX MELACOM ON 19:00:00 19:15:20 21:15:20
MEX Start recording 23:21:12 23:36:32 01:36:32
PHX Entry 23:30:59 23:46:19 01:46:19
PHX Chute deployment 23:34:42 23:50:02 01:50:02
PHX Lander separation 23:37:41 23:53:01 01:53:01
PHX Landing 23:38:21 23:53:41 01:53:01
MEX Stop recording 23:47:12 00:02:32 02:02:32
MEX Slew to Earth pointing 23:47:12 00:02:32 02:02:32
MEX 1st MELACOM data download start 00:25:00 00:40:20 02:40:20 Via DSS-15 & DSS-25
MEX 1st MELACOM data download end 00:42:00 00:57:20 02:57:20
MEX MELACOM data available to NASA 00:42:00 00:57:20 02:57:20
MEX 2nd MELACOM data download start 00:42:00 00:57:20 02:57:20 Via DSS-15 & DSS-25
MEX 2st MELACOM data download end 00:59:00 01:14:20 03:14:20
MEX Slew to PHX pointing 05:35:33 05:50:53 07:50:53
MEX 1st PHX O/F start 06:12:00 06:27:20 08:27:20 MELACOM ON
MEX 1st PHX O/F end 06:23:00 06:38:20 08:38:20 MELACOM OFF
MEX Slew to Earth pointing 06:26:14 06:41:34 08:41:34
MEX 3rd MELACOM data download 08:25:00 08:40:20 10:40:20 Via ESTRACK New Norcia
MEX 3rd MELACOM data download end 08:42:00 08:57:20 10:57:20
MEX 1st PHX O/F data download start 08:45:00 09:00:20 11:00:20 Via ESTRACK New Norcia
MEX 1st PHX O/F data download end 09:01:00 09:16:20 11:16:20