Herschel and Planck launch timeline

Herschel separates from upper stage
ARCHIVE CONTENT 11 MAY. 2009 publication date 5302 Views

There's a buzz in the Main Control Room as the launch of Herschel and Planck gets closer. The two satellites are scheduled to launch together at 15:12 CEST, 14 May, on an Ariane 5 from ESA's Spaceport in Kourou, French Guiana. Several critical events are planned leading up to and after launch (Web updated 13 May 09:40 CEST).

After launch, Herschel and Planck will be headed to L2, the second Lagrange point of the Sun-Earth system, where they will operate from independent orbits.


Herschel and Planck launch configuration

L2 is a local gravitational point that is fixed in the Earth-Sun system and is situated on Earth’s night-side. It is an excellent location for both Herschel and Planck: it allows them to shield their sensitive instruments from solar radiation which may otherwise disturb observations and offers good sky visibility. If they were placed in orbit around Earth, heat from our planet, the Moon and the Sun would interfere with the instruments and telescopes, reducing sensitivity.


Ariane 5 fairing ejection

Both satellites have now been integrated with the launcher; the combination measures approximately 11 m in height and 4.5 m in width, with a weight of about 5.7 tonnes.

The critical milestones before launch include the launch readiness review, held on 9 May, and roll-out to the launch pad on 13 May. The launch also marks the beginning of the Launch and Early Orbit phase (LEOP), during which mission controllers will monitor the satellites 22 hr/day via ESA's ground stations at New Norcia and Perth, Australia; Maspalomas and Cebreros, Spain; and Kourou, French Guiana.


The Ariane 5’s solid boosters separate about 2.5 minutes into the launch and the fairing is jettisoned about 50 seconds later. The upper stage separates and its engine ignites about 9 minutes into the launch.

The velocity of the composite that includes both satellites will be about 10 km/s just before the satellites go their own way. Separation of Herschel from the upper stage is scheduled for 15:38 CEST, about 26 minutes into the launch. The 'Sylda' (a support structure for Herschel that also forms a protective cover for Planck) will be jettisoned 1.5 minutes later and Planck will follow at about 15:40 CEST, just under 29 minutes into the launch.


Separation will occur above the east coast of Africa, at about 1100 km altitude for Herschel, and at about 1700 km altitude for Planck, which separates some 2.5 mins after Herschel. After separation, the two satellites will have slightly different velocities.

Herschel's final orbit will be a quasi-halo orbit with an average distance of 800 000 km from L2. The final orbit for Planck will be a Lissajous orbit, with an amplitude of 400 000 km.


The launcher will set the satellites directly on the path to L2. This means that no injection manoeuvre will be necessary for Herschel; the satellite will be close to its halo orbit around L2 right from separation. One major manoeuvre is planned to fine-tune the orbit about 24 hours after launch.

Planck will also be in orbit around L2 at separation, but since the amplitude of its orbit is half that of Herschel, engineers will execute manoeuvres to reduce its orbit to half that of the original. The first manoeuvre is planned about 30 hours after launch.

An expanded version of the timeline covering all critical events around and after launch is below.


ESA web coverage

Regular coverage leading up to and after launch, covering these critical milestones will be available at the following ESA websites:

Additional information is available via the following:

Timeline of critical events

Note:
- Times given as hours:minutes:seconds in Central European Summer Time (CEST) = UT + 2 hrs
- TCM: Trajectory correction manoeuvre
- LEOP: Launch and Early Orbit Phase
- ESOC: European Space Operations Centre
- - All times subject to change

Critical event

Time +/- liftoff

Time (CEST)

Launch Readiness Review

-5 days

9 May

Roll out to launch pad

-1 day

13:40:00, 13 May

ESOC GO/NO-GO for launch

-00:30:00

14:42:00
14 May

Herschel on internal power

-00:15:00

14:57:00

Planck on internal power

-00:11:00

15:01:00

Start of Ariane 5 automatic sequence

-00:07:00

15:05:00

Final confirmation of spacecraft & ground segment readiness

-00:06:30

15:05:30

Last time to declare NOGO

-00:04:30

15:07:30

Inertial platform release

-00:00:03

15:11:57

Launch
(Window open for 55 mins)

00:00:00

15:12:00

Ariane 5 solid rocket booster ignition & liftoff

00:00:07

15:12:07

Solid boosters jettisoned

00:02:18

15:14:18

Fairing jettisoned

00:04:02

15:16:02

Main cryogenic stage extinction and upper stage separation

00:08:55

15:20:55

Upper stage ignition

00:09:05

15:21:05

Upper stage extinction

00:24:30

15:36:40

Herschel separates

00:25:58

15:37:58

Sylda separates

00:27:24

15:39:24

Planck separates

00:28:29

15:40:29

 

Herschel

 Time
(CEST)

Planck

 Time
(CEST)

First signal acquisition
(via New Norcia)

15:49:00

First signal acquisition
(via Perth)

15:49:00

TCM 1a

14:36:00
15 May

TCM 1a

21:27:00
15 May

TCM 1b

13:42
17 May

TCM 1b

14:43:00
17 May

--

--

TCM 2

6 June

--

--

TCM 3

3 July

LEOP Phase out starts

16 May

LEOP Phase out starts

18 May

Commissioning begins

16 May

Commissioning begins

18 May

 