Mission Summary
Christer Fuglesang will also be undertaking an experiment programme for the European Space Agency as part of the Celsius Mission though this is not currently fixed to a specific day in the mission timeline.
Flight Day 1 - Launch
Launch from Kennedy Space Center
Shuttle to On-orbit configuration
Activation of Spacehab
Activation of Shuttle robotic arm
Test the Space Shuttle’s robotic arm
Checking the Space Shuttle heat shields using robotic arm
EVA preparation including testing EVA suits
Preparations for docking with the ISS
Rendezvous and dock with the ISS including Shuttle backflip manoeuvre to check heat shields
Hatches opened
P5 truss moved out of Shuttle cargo bay to overnight parked position using Shuttle and ISS robotic arms
Transfer equipment from Shuttle to airlock
Checks on EVA suits. EVA tools prepared
Fuglesang and Curbeam sealed in airlock for the night to help flush nitrogen out of the blood pre-EVA
EVA prep
P5 truss moved to installation location with Station robotic arm
Solar arrays fixed in position
EVA: Attach P5 truss to P4 truss, relocate grapple fixture on P5, and remove and replace camera on S1 truss
Transfer cargo between Shuttle and ISS
Switch over power responsibilities from 4B solar array on P6 truss to 4A solar array on P4 truss
Retract 4B solar array
Activate Solar Alpha Rotary Joint for rotating solar arrays on P4 truss section
Fill and activate port-side cooling loop
Fuglesang and Curbeam sealed in airlock for the night to help flush nitrogen out of the blood pre-EVA
Switch ISS systems to power channels 1 and 4
Shut down power channels 2 and 3
EVA: Reconfigure power on power channels 2 and 3 around S0 and Z1 truss sections. Activate port-side thermal control system, Activate power channels 2 and 3. Relocate Crew and Equipment Translation Aid (CETA) carts from starboard to port-side of Mobile Transporter.
Transfer cargo between Shuttle and ISS
Fill and activate starboard cooling loop
Curbeam and Williams sealed in airlock for the night to help flush nitrogen out of the blood pre-EVA
Switch ISS systems to power channels 2 and 3
Shut down power channels 1 and 4
EVA: Reconfigure power on power channels 1 and 4 around S0 and Z1 truss sections. Activate starboard thermal control system, Activate power channels 1 and 4. Stow debris protection panels on mating adapter outside of ISS Node 1. Install grapple bar on thermal box
Configure port and starboard thermal control power supply
Transfer of equipment and supplies
EVA preparations, including reconfiguring EVA suit to fit Fuglesang
Fuglesang and Curbeam sealed in airlock for the night to help flush nitrogen out of the blood pre-EVA
EVA: Aid retraction P6 solar array
Clean-up after EVA
Final transfer of equipment and supplies
Hatch Closure
Undock
Station flyover
Thruster burn
Late inspection of Shuttle heat shields
Landing preparations
Shuttle to landing configuration
Landing preparations
Deorbit burn
Reentry
Landing at Kennedy Space Center